Work on our boiler, by LNWR Heritage, at Crewe, is progressing very well.

The new front tubeplate is in position, and is being drilled, prior to riveting:-

Three quarters of the rivets for the foundation ring are in place:-

A new bottom half to the smokebox is being welded into place, because of corrosion:-

Work is also progressing well on the frames. Preparations are underway to align the slidebars, before they are re-fitted:-